From the principal’s experience · Supply chain

Take the pressure off. Then fix the plant.

A Fortune 100 skincare manufacturer couldn’t keep its promises to customers while its own plant was being repaired. I led the supply chain team that moved more than 30 million units of production to outside manufacturers, so the plant could get well without the shelves going empty.

+49%

Product availability

110

Products qualified at contract manufacturers

30M+

Units of production taken off the home plant

12 mo

To remediate the plant, on an expedited timeline

Clean personal care filling lines running side by side with unlabeled bottles

01 · Situation

Under pressure, and under the microscope.

A product recall had affected about 70% of the company’s product. Service levels had dropped to around 60%, well below the 80%-plus the business normally ran.

Market share and on-time deliveries were slipping, and every decision was under intense scrutiny.

02 · Problem

One plant couldn’t do both jobs.

The home plant had to keep up with customer demand and fix its own operations at the same time. It couldn’t do both well.

The answer was to qualify more than 30% of the in-house product portfolio at third-party contract manufacturers. That would free up capacity so the plant could focus on getting healthy.

03 · Action

Move the right products to the right partners.

  1. Qualify 110 products. I led the supply chain team through qualifying each product at outside manufacturers.
  2. Decide with data. Each sourcing decision weighed cost structure, material availability, quality record, and proximity to where demand was forecast, to keep freight down.
  3. Plan supply and demand together. SAP, demand planning, supply planning, and inventory management kept product flowing across both the plant and its partners.
  4. Give the Board one clear picture. I built and maintained a data model and dashboard, presented every week to the Board and senior executives.

04 · Result

The shelves stayed stocked. The plant got well.

The dual-sourcing program took more than 30 million units of production off the home plant. That breathing room let the facility and its operations be remediated in an expedited 12 months.

Product availability improved 49%.

The in-house product portfolio

30%+Stayed at the home plant
Qualified at contract manufacturers: 110 products, 30M+ units

Service level

Normal: 80%+

~60% at the low point, after the recall

Moving a third of the portfolio gave the plant room to heal in 12 months. Product availability improved 49%.

Sometimes the fastest way to fix a plant is to stop asking it to do everything at once.

Relieve the pressure first. Then fix what’s underneath.